The integrated skid-mounted device of PetroChina's high-sulfur ground construction project undertaken by Venus successfully passed the start-up acceptance.


As the first self-built high-sulfur ground construction project of PetroChina Southwest Oil and Gas Field Company, the integrated skid-mounted device undertaken by Jinxing Co., Ltd. is the high-sulfur core device of the whole project. In view of the construction characteristics and difficulties of high sulfur resistance projects, the company's project management department carefully organized the design, procurement, production, quality inspection, data and other departments to carry out systematic planning, and carried out fine management.

|

 

Welding experts guide the welding work on site

The welder entrance examination was specifically adopted to strengthen the training of welder skills. Strengthen quality management; Sulfur-resistant regional isolation construction, planning construction site visual management.

 

 

 

Visual operation on site

 

material storage management

 


The meeting room of the inspection team and the members of the project team of Venus Company discussed the project situation.

Recently, the key project department of PetroChina Southwest Oil and Gas Field, the project construction unit, organized EPC unit and supervision unit to inspect the preparation for high sulfur resistance of the project. The inspection team spoke highly of the construction organization planning, site preparation, and site management of Jinxing Co., Ltd., and the project passed the start acceptance smoothly.